Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-035-10-40 04-0T14F4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SOL-37-8.0/10.5 Federal Project: NONE Progress payment No. 47 Payment period ending: 11-19-10 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 361,302.50 0.00 2.a. Extra Work 60,561.61 1,950.69 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 421,864.11 1,950.69 5. Mobilization 51,000.00 0.00 6. Total Work Completed 472,864.11 7. Deductions -1,801.00 0.00 8. a.Contract Retentions -20,995.67 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 20,995.67 0.00 9. Total pay to Contractor 471,063.11 1,950.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,950.69