Dept. of Trans. PROGRESS Serial No. Contract No. 26-096-13-39 04-0V4604 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 8% Location: Federal Project: 04-AL-24-0.0/6.0 NONE Progress payment No. 001 Payment period ending: 02-27-26 MONTEREY MECHANICAL CO 8275 SAN LEANDRO ST OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 484,710.11 484,710.11 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 484,710.11 484,710.11 5. Mobilization 6. Total Work Completed 484,710.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 484,710.11 484,710.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 484,710.11