Dept. of Trans. PROGRESS Serial No. Contract No. 21-267-10-42 04-0W1204 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 37% Location: Federal Project: 04-SM-84-17.2/17.2 NONE Progress payment No. 006 Payment period ending: 09-09-21 GRANITE CONSTRUCTION COMPANY 715 COMSTOCK ST SANTA CLARA CA 95054 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 914,960.61 370,394.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 914,960.61 370,394.16 5. Mobilization 6. Total Work Completed 914,960.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 914,960.61 370,394.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 370,394.16