Dept. of Trans. PROGRESS Serial No. Contract No. 24-159-11-58 04-0X0404 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 58% Location: Federal Project: 04-SF-101-2.9/2.9 NONE Progress payment No. 003 Payment period ending: 06-07-24 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 337,025.31 57,901.77 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 337,025.31 57,901.77 5. Mobilization 6. Total Work Completed 337,025.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 337,025.31 57,901.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,901.77