Dept. of Trans. PROGRESS Serial No. Contract No. 26-136-09-40 04-0X3304 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 81% Location: Federal Project: 04-SM-84-28.0/2.0 NONE Progress payment No. 009 Payment period ending: 04-30-26 MONTEREY MECHANICAL CO 8275 SAN LEANDRO ST OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 780,673.01 21,587.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 780,673.01 21,587.24 5. Mobilization 6. Total Work Completed 780,673.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 780,673.01 21,587.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,587.24