Dept. of Trans. PROGRESS Serial No. Contract No. 25-324-15-19 04-0X5804 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 72% Location: Federal Project: 04-VAR NONE Progress payment No. 002 Payment period ending: 11-20-25 GBA ENGINEERING INC 18543 YORBA LINDA BLVD 394 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 137,705.60 50,905.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 137,705.60 50,905.60 5. Mobilization 70,000.00 0.00 6. Total Work Completed 207,705.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 207,705.60 50,905.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,905.60