Dept. of Trans. PROGRESS Serial No. Contract No. 25-198-18-31 04-0X6304 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 17% Location: Federal Project: 04-SCL-101-T4.5/R17.5 NONE Progress payment No. 001 Payment period ending: 07-20-25 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 473,993.75 473,993.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 473,993.75 473,993.75 5. Mobilization 128,250.00 128,250.00 6. Total Work Completed 602,243.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 602,243.75 602,243.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 602,243.75