Dept. of Trans. PROGRESS Serial No. Contract No. 22-294-09-29 04-0Y1104 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 100% Location: Federal Project: 04-ALA-84-12.5/12.5 NONE Progress payment No. 004 Payment period ending: 10-20-22 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 412,368.88 68,735.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 412,368.88 68,735.52 5. Mobilization 6. Total Work Completed 412,368.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -10,821.08 -6,873.55 c. Reduction after 95% Comp. 9. Total pay to Contractor 401,547.80 61,861.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,861.97