Dept. of Trans. FINAL Serial No. Contract No. 25-017-11-56 04-0Y2304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-NAP-29-0.0/5.1 NONE Progress payment No. 006 Payment period ending: 10-26-23 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 694,226.83 0.00 2. a. Extra Work 158,645.21 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 852,872.04 0.00 5. Mobilization 6. Total Work Completed 852,872.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 852,872.04 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00