Dept. of Trans. PROGRESS Serial No. Contract No. 24-291-10-30 04-0Y2604 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 28% Location: Federal Project: 04-SON-121-R7.3/11.6 NONE 04-NAP-121-0.3/2.0 Progress payment No. 001 Payment period ending: 10-20-24 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 118,132.32 118,132.32 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 118,132.32 118,132.32 5. Mobilization 100,000.00 100,000.00 6. Total Work Completed 218,132.32 7. Deductions -100,000.00 -100,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 118,132.32 118,132.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,132.32