Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-296-12-19 04-0Y3404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SM-35-2.2/4.5 NONE 04-SM-84-12.0/17.8 Progress payment No. 002 Payment period ending: 09-13-23 QA CONSTRUCTORS INC 850 S. VAN NESS AVE #35 SAN FRANCISCO CA 94110 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 655,279.00 52,771.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 655,279.00 52,771.20 5. Mobilization 6. Total Work Completed 655,279.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 655,279.00 52,771.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,771.20