Dept. of Trans. PROGRESS Serial No. Contract No. 22-180-08-55 04-0Y4804 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 60% Location: Federal Project: 04-SM-1-38.1/38.1 NONE Progress payment No. 002 Payment period ending: 06-19-22 REDWOOD ENGINEERING CONSTRUCTION 416 D ST REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 356,259.86 153,454.28 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 356,259.86 153,454.28 5. Mobilization 6. Total Work Completed 356,259.86 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 356,259.86 153,454.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 153,454.28