Dept. of Trans. PROGRESS Serial No. Contract No. 23-054-16-11 04-0Y5004 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 13% Location: Federal Project: 04-SCL-280-2.9/2.9 NONE Progress payment No. 003 Payment period ending: 01-30-23 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 503,188.36 19,688.38 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 503,188.36 19,688.38 5. Mobilization 6. Total Work Completed 503,188.36 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 503,188.36 19,688.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,688.38