Dept. of Trans. PROGRESS Serial No. Contract No. 22-245-15-47 04-0Y6104 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 75% Location: Federal Project: 04-SM-84-24.5/24.8 NONE Progress payment No. 004 Payment period ending: 08-20-22 QA CONSTRUCTORS INC 850 S. VAN NESS AVE #35 SAN FRANCISCO CA 94110 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 597,888.57 226,208.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 597,888.57 226,208.24 5. Mobilization 6. Total Work Completed 597,888.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -22,620.82 -22,620.82 c. Reduction after 95% Comp. 9. Total pay to Contractor 575,267.75 203,587.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 203,587.42