Dept. of Trans. PROGRESS Serial No. Contract No. 24-200-19-54 04-0Y8304 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 40% Location: Federal Project: 04-VAR NONE Progress payment No. 001 Payment period ending: 07-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 190,262.50 190,262.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 190,262.50 190,262.50 5. Mobilization 149,925.00 149,925.00 6. Total Work Completed 340,187.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 340,187.50 340,187.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 340,187.50