Dept. of Trans. PROGRESS Serial No. Contract No. 24-257-19-44 04-0Y8404 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 18% Location: Federal Project: 04-VAR NONE Progress payment No. 001 Payment period ending: 09-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 667,611.23 667,611.23 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 667,611.23 667,611.23 5. Mobilization 294,500.00 294,500.00 6. Total Work Completed 962,111.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 962,111.23 962,111.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 962,111.23