Dept. of Trans. PROGRESS Serial No. Contract No. 14-265-07-02 04-1123H4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 88% 04-SM-1-38.2/39.7 Federal Project: SM-9790(13) Progress payment No. 11 Payment period ending: 09-20-14 EMPIRE LANDSCAPING INC P O BOX 35 DAVIS CA 95616 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 789,920.40 34,110.40 2.a. Extra Work 115,532.17 0.00 b. Adjustment Comp. 5,344.39 0.00 3. Materials on Hand 4. Earned Subject to Retention 910,796.96 34,110.40 5. Mobilization 75,000.00 0.00 6. Total Work Completed 985,796.96 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 985,796.96 34,110.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,110.40