Dept. of Trans. PROGRESS Serial No. Contract No. 11-327-10-42 04-1123J4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SM-1-39.6/40.1 Federal Project: ACST-1187(12) P-1187(12) Progress payment No. 30 Payment period ending: 11-20-11 ODYSSEY LANDSCAPING COMPANY INC 5400 HIGHWAY 12 LODI CA 95242 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 542,553.98 6,607.50 2.a. Extra Work 141,212.49 4,044.68 b. Adjustment Comp. 2,563.60 0.00 3. Materials on Hand 4. Earned Subject to Retention 686,330.07 10,652.18 5. Mobilization 20,697.55 0.00 6. Total Work Completed 707,027.62 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 706,027.62 9,652.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,652.18