Dept. of Trans. PROGRESS Serial No. Contract No. 06-355-10-35 04-1123K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 36% 04-SM-1-39.6/40.1 Federal Project: ER-1187(10) Progress payment No. 09 Payment period ending: 12-20-06 DISNEY CONSTRUCTION INC 635 OCCIDENTAL AVENUE SAN MATEO CA 94402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,330,843.50 1,196,565.50 2.a. Extra Work 2,271,230.22 469,620.70 b. Adjustment Comp. 3. Materials on Hand 197,586.00 -41,274.00 4. Earned Subject to Retention 14,799,659.72 1,624,912.20 5. Mobilization 3,166,666.35 0.00 6. Total Work Completed 17,768,740.07 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,966,326.07 1,624,912.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,624,912.20