Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-08-14 04-1123K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 83% 04-SM-1-39.6/40.1 Federal Project: ER-1187(10) Progress payment No. 23 Payment period ending: 02-20-08 DISNEY CONSTRUCTION INC 1279 LINDA MAR SHOP. CEN.#313 PACIFICA, CA 94044 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,961,746.15 1,162,692.50 2.a. Extra Work 2,960,606.84 104,820.52 b. Adjustment Comp. 110,655.51 5,443.57 3. Materials on Hand 146,952.00 -22,272.00 4. Earned Subject to Retention 30,179,960.50 1,250,684.59 5. Mobilization 3,333,333.00 0.00 6. Total Work Completed 33,366,341.50 7. Deductions -15,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,498,293.50 1,240,684.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,240,684.59