Dept. of Trans. PROGRESS Serial No. Contract No. 11-059-10-00 04-1123U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 78% 04-SM-1-38.0/38.6 Federal Project: 04-SM-1-39.6/40.4 ACST-1187(11) P-1187(11) ER-1187(11) Progress payment No. 52 Payment period ending: 02-20-11 KIEWIT INFRASTRUCTURE WEST CO 3555 FARNAM STREET, STE E200 OMAHA, NE 68131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 176,776,396.86 4,283,041.78 2.a. Extra Work 10,707,914.21 691,925.86 b. Adjustment Comp. 10,613,246.63 26,822.87 3. Materials on Hand 2,460,920.50 0.00 4. Earned Subject to Retention 200,558,478.20 5,001,790.51 5. Mobilization 27,236,600.00 0.00 6. Total Work Completed 225,334,157.70 7. Deductions -6,317,644.00 -175,536.75 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 221,477,434.20 4,826,253.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,826,253.76