Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 11-336-08-09 04-1123U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 78% 04-SM-1-38.0/38.6 Federal Project: 04-SM-1-39.6/40.4 ACST-1187(11) P-1187(11) ER-1187(11) Progress payment No. 62 Payment period ending: 11-30-11 KIEWIT INFRASTRUCTURE WEST CO 3555 FARNAM STREET, STE E200 OMAHA, NE 68131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 208,097,134.93 -3,855,000.00 2.a. Extra Work 13,650,508.89 3,658.94 b. Adjustment Comp. 40,410,461.21 25,506,431.03 3. Materials on Hand 1,661,110.00 -123,866.53 4. Earned Subject to Retention 263,819,215.03 21,531,223.44 5. Mobilization 27,236,600.00 0.00 6. Total Work Completed 289,394,705.03 7. Deductions -7,519,573.84 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 283,536,241.19 21,531,223.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,531,223.44