Dept. of Trans. PROGRESS Serial No. Contract No. 03-237-11-59 04-120614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 51% 04-NAP-29-11.6/13.5 Federal Project: ACST-P029(89) P-P029(89) Progress payment No. 19 Payment period ending: 08-20-03 R AND L BROSAMER INC P O BOX 238 ALAMO CA 945070238 Escrow No. 01896 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,185,838.68 1,698,286.48 2.a. Extra Work 1,005,609.07 37,942.10 b. Adjustment Comp. 2,080,661.56 8,300.00 3. Materials on Hand 743,775.35 -101,612.14 4. Earned Subject to Retention 26,015,884.66 1,642,916.44 5. Mobilization 3,450,000.00 0.00 6. Total Work Completed 28,722,109.31 7. Deductions -44,300.00 -2,000.00 8. a.Contract Retentions -1,300,794.23 -82,145.82 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,120,790.43 1,558,770.62 10. Reduction Amt to Escrow 11. Payment to Escrow 1,300,790.00 12. Net Pymt. this Estimate 1,558,770.62