Dept. of Trans. PROGRESS Serial No. Contract No. 03-108-12-45 04-124784 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 5% 14% 04-SCL-5736 Federal Project: NONE Progress payment No. 03 Payment period ending: 04-20-03 R G W CONSTRUCTION INC BARRY SWENSON BUILDER A JOINT VENTURE P O BOX 2910 LIVERMORE CA 94550 Escrow No. 02052 Total Estimate This Estimate 1. Contract Itms Without Mobil. 284,757.27 149,822.27 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 284,757.27 149,822.27 5. Mobilization 6. Total Work Completed 284,757.27 7. Deductions 8. a.Contract Retentions -28,475.73 -14,982.23 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 256,281.54 134,840.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 134,840.04