Dept. of Trans. PROGRESS Serial No. Contract No. 04-202-10-55 04-124784 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 04-SCL-5736 Federal Project: NONE Progress payment No. 18 Payment period ending: 07-20-04 R G W CONSTRUCTION INC BARRY SWENSON BUILDER A JOINT VENTURE P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02052 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,373,088.52 0.00 2.a. Extra Work 469,286.98 234,764.36 b. Adjustment Comp. 142,553.85 -41,524.92 3. Materials on Hand 4. Earned Subject to Retention 5,984,929.35 193,239.44 5. Mobilization 6. Total Work Completed 5,984,929.35 7. Deductions -27,088.22 0.00 8. a.Contract Retentions -299,246.47 -9,661.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,658,594.66 183,577.47 10. Reduction Amt to Escrow 11. Payment to Escrow 299,240.00 12. Net Pymt. this Estimate 183,577.47