Dept. of Trans. PROGRESS Serial No. Contract No. 01-201-17-01 04-128204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 9% 04-CC-680-13.7/14.9 Federal Project: 04-CC-24-R8.2/9.1 IR ACNH-P024(26) Progress payment No. 06 Payment period ending: 07-20-01 AMLAND 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 01664 Total Estimate This Estimate 1. Contract Itms Without Mobil. 304,823.00 61,696.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -5,147.90 4. Earned Subject to Retention 304,823.00 56,548.10 5. Mobilization 123,500.00 0.00 6. Total Work Completed 428,323.00 7. Deductions -13,597.06 0.00 8. a.Contract Retentions -20,597.46 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 394,128.48 56,548.10 10. Reduction Amt to Escrow 11. Payment to Escrow 20,590.00 12. Net Pymt. this Estimate 56,548.10