Dept. of Trans. PROGRESS Serial No. Contract No. 02-168-15-10 04-128204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 27% 04-CC-680-13.7/14.9 Federal Project: 04-CC-24-R8.2/9.1 IR ACNH-P024(26) Progress payment No. 16 Payment period ending: 06-20-02 AMLAND 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 01664 Total Estimate This Estimate 1. Contract Itms Without Mobil. 758,299.30 25,121.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 758,299.30 25,121.00 5. Mobilization 130,000.00 0.00 6. Total Work Completed 888,299.30 7. Deductions -18,268.70 0.00 8. a.Contract Retentions -37,914.97 -1,256.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 832,115.63 23,864.95 10. Reduction Amt to Escrow 11. Payment to Escrow 37,910.00 12. Net Pymt. this Estimate 23,864.95