Dept. of Trans. PROGRESS Serial No. Contract No. 01-026-15-27 04-128214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 51% 04-CC-680-15.2/R17.3 Federal Project: ACIM-680-1(46) Progress payment No. 21 Payment period ending: 01-20-01 SOUTH SHORES RESIDENTIAL AND COMMERCIAL DEVELOPMENT CORPORATION 2200 SOUTH FAIRVIEW SANTA ANA, CA 92704 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 735,327.50 5,208.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 735,327.50 5,208.00 5. Mobilization 85,000.00 0.00 6. Total Work Completed 820,327.50 7. Deductions -10,317.40 -2,250.00 8. a.Contract Retentions -36,766.38 -260.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 773,243.72 2,697.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,697.60