Dept. of Trans. PROGRESS Serial No. Contract No. 12-114-14-23 04-129654 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 81% 04-SON-101-13.9/15.5 Federal Project: NONE Progress payment No. 41 Payment period ending: 04-20-12 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,456,341.78 197,672.66 2.a. Extra Work 2,013,181.76 36,686.22 b. Adjustment Comp. 939,878.89 0.00 3. Materials on Hand 584,133.81 32,265.28 4. Earned Subject to Retention 31,993,536.24 266,624.16 5. Mobilization 3,620,000.00 0.00 6. Total Work Completed 35,029,402.43 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 35,613,536.24 266,624.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,624.16