Dept. of Trans. PROGRESS Serial No. Contract No. 04-168-12-48 04-130214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 16% 04-SON-101-13.7/14.1 Federal Project: ACNH-Q101(27) CML-5379(10) Progress payment No. 03 Payment period ending: 06-20-04 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02158 Total Estimate This Estimate 1. Contract Itms Without Mobil. 295,412.85 64,848.25 2.a. Extra Work 5,324.43 5,324.43 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 300,737.28 70,172.68 5. Mobilization 158,250.00 52,750.00 6. Total Work Completed 458,987.28 7. Deductions -11,970.00 -570.00 8. a.Contract Retentions -30,073.73 -7,017.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 416,943.55 115,335.41 10. Reduction Amt to Escrow 11. Payment to Escrow 30,070.00 12. Net Pymt. this Estimate 115,335.41