Dept. of Trans. PROGRESS Serial No. Contract No. 06-167-07-35 04-130524 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 0% 04-ALA-5746 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-20-06 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 728,774.10 637,136.10 2.a. Extra Work 1,800.00 1,800.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 730,574.10 638,936.10 5. Mobilization 6. Total Work Completed 730,574.10 7. Deductions -60,300.00 -20,100.00 8. a.Contract Retentions -73,057.41 -63,893.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 597,216.69 554,942.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 554,942.49