Dept. of Trans. PROGRESS Serial No. Contract No. 07-053-14-29 04-130524 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 80% 04-ALA-5746 Federal Project: NONE Progress payment No. 10 Payment period ending: 02-20-07 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 02262 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,521,193.18 384,956.00 2.a. Extra Work 25,155.61 10,022.60 b. Adjustment Comp. 16,406.19 -45.00 3. Materials on Hand 4. Earned Subject to Retention 4,562,754.98 394,933.60 5. Mobilization 6. Total Work Completed 4,562,754.98 7. Deductions -67,000.00 0.00 8. a.Contract Retentions -228,137.75 -19,746.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,267,617.23 375,186.92 10. Reduction Amt to Escrow 11. Payment to Escrow 228,130.00 12. Net Pymt. this Estimate 375,186.92