Dept. of Trans. PROGRESS Serial No. Contract No. 07-355-11-03 04-130524 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 04-ALA-5746 Federal Project: NONE Progress payment No. 21 Payment period ending: 12-20-07 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 02262 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,501,428.54 11,589.00 2.a. Extra Work 255,498.34 38,049.51 b. Adjustment Comp. 60,032.21 -9,438.21 3. Materials on Hand 4. Earned Subject to Retention 8,816,959.09 40,200.30 5. Mobilization 6. Total Work Completed 8,816,959.09 7. Deductions -67,000.00 0.00 8. a.Contract Retentions -440,847.95 -2,010.01 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,309,111.14 38,190.29 10. Reduction Amt to Escrow 11. Payment to Escrow 440,840.00 12. Net Pymt. this Estimate 38,190.29