Dept. of Trans. PROGRESS Serial No. Contract No. 07-237-15-07 04-132954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 96% 04-MRN-580-2.6/ .0 Federal Project: NONE Progress payment No. 08 Payment period ending: 08-20-07 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 704,088.14 61,672.05 2.a. Extra Work 83,657.05 43,764.76 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 787,745.19 105,436.81 5. Mobilization 82,000.00 0.00 6. Total Work Completed 869,745.19 7. Deductions -16,140.00 -5,000.00 8. a.Contract Retentions -39,387.26 -5,271.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 814,217.93 95,164.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,164.97