Dept. of Trans. PROGRESS Serial No. Contract No. 06-324-18-26 04-150144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 04-ALA-580-0.0/ .0 Federal Project: ACIM-580-1(47) Progress payment No. 08 Payment period ending: 11-20-06 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,042,756.70 70,570.00 2.a. Extra Work 4,795.72 0.00 b. Adjustment Comp. -2,735.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,044,817.42 70,570.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 1,144,817.42 7. Deductions -10,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,134,317.42 70,570.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,570.00