Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-002-12-03 04-150144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-580-0.0/ .0 Federal Project: ACIM-580-1(47) Progress payment No. 09 Payment period ending: 12-18-06 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,064,537.20 21,780.50 2.a. Extra Work 25,773.65 20,977.93 b. Adjustment Comp. -2,735.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,087,575.85 42,758.43 5. Mobilization 100,000.00 0.00 6. Total Work Completed 1,187,575.85 7. Deductions -12,500.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,175,075.85 40,758.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,758.43