Dept. of Trans. PROGRESS Serial No. Contract No. 01-292-11-44 04-150404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 04-SM-92-R12.1/R18.8 Federal Project: 04-ALA-92-R0.0/6.3 NONE Progress payment No. 12 Payment period ending: 10-19-01 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958231430 Escrow No. 01615 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,074,111.00 186,589.00 2.a. Extra Work b. Adjustment Comp. -80,972.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,993,138.50 186,589.00 5. Mobilization 370,000.00 0.00 6. Total Work Completed 6,363,138.50 7. Deductions 8. a.Contract Retentions -299,656.93 -9,329.45 b. Unsatisfactory Prog. -27,586.32 -9,329.45 c. Reduction after 95% Comp. 9. Total pay to Contractor 6,035,895.25 167,930.10 10. Reduction Amt to Escrow 11. Payment to Escrow 299,650.00 12. Net Pymt. this Estimate 167,930.10