Dept. of Trans. FINAL Serial No. Contract No. 02-056-13-53 04-150404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-92-R12.1/R18.8 Federal Project: 04-ALA-92-R0.0/6.3 NONE Progress payment No. 15 Payment period ending: 11-30-01 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 958231430 Escrow No. 01615 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,133,646.00 0.00 2.a. Extra Work 62,246.40 62,246.40 b. Adjustment Comp. -86,908.50 -5,936.00 3. Materials on Hand 4. Earned Subject to Retention 6,108,983.90 56,310.40 5. Mobilization 370,000.00 0.00 6. Total Work Completed 6,478,983.90 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -300,819.63 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 300,819.63 0.00 9. Total pay to Contractor 6,478,983.90 66,310.40 10. Reduction Amt to Escrow -300,810.00 0.00 11. Payment to Escrow 300,810.00 12. Net Pymt. this Estimate 66,310.40