Dept. of Trans. PROGRESS Serial No. Contract No. 10-235-10-16 04-150474 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 53% 04-SM-280-0.0/27.4 Federal Project: SARR-2801(122) A-2801(122) Progress payment No. 07 Payment period ending: 08-20-10 STEINY AND COMPANY INC P O BOX 3008 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 786,034.90 311,258.90 2.a. Extra Work 12,900.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 798,934.90 311,258.90 5. Mobilization 10,000.00 0.00 6. Total Work Completed 808,934.90 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 808,934.90 311,258.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 311,258.90