Dept. of Trans. PROGRESS Serial No. Contract No. 07-022-12-30 04-150774 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 81% 04-CC-4-0.7/31.1 Federal Project: NONE Progress payment No. 05 Payment period ending: 01-20-07 STEINY AND COMPANY INC P O BOX 3008 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 754,803.00 145,206.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 754,803.00 145,206.00 5. Mobilization 53,902.00 2,695.10 6. Total Work Completed 808,705.00 7. Deductions -500.00 0.00 8. a.Contract Retentions -37,740.15 -7,260.30 b. Unsatisfactory Prog. -25,569.44 -7,260.30 c. Reduction after 95% Comp. 9. Total pay to Contractor 744,895.41 133,380.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,380.50