Dept. of Trans. PROGRESS Serial No. Contract No. 07-079-07-57 04-150924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 100% 04-ALA-580-0.1/12.5 Federal Project: 04-SJ-580-11.0/15.3 ACIM-000C(280) 04-SJ-205-L0.0/2.9 Progress payment No. 07 Payment period ending: 03-20-07 TENNYSON ELECTRIC INC 7275 NATIONAL DR LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 602,934.40 14,130.00 2.a. Extra Work 27,320.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 630,254.40 14,130.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 650,254.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -55,869.85 -1,413.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 594,384.55 12,717.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,717.00