Dept. of Trans. PROGRESS Serial No. Contract No. 06-263-07-26 04-151054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 19% 04-ALA-580-17.0/22.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-20-06 TOP GRADE CONSTRUCTION INC 50 CONTRACTORS STREET LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 140,300.00 140,300.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 140,300.00 140,300.00 5. Mobilization 117,500.00 117,500.00 6. Total Work Completed 257,800.00 7. Deductions 8. a.Contract Retentions -14,030.00 -14,030.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 243,770.00 243,770.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 243,770.00