Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-14-10 04-151284 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 91% 04-VAR Federal Project: ACST-X085(38) P-X085(38) Progress payment No. 13 Payment period ending: 08-20-07 AMLAND 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,248,551.75 0.00 2.a. Extra Work 61,372.36 31,742.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,309,924.11 31,742.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 1,409,924.11 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,409,924.11 31,742.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,742.00