Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-08-22 04-151374 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 43% 04-SCL-101-28.4/51.8 Federal Project: 04-SCL-237-4.6/6.9 STP-X085(46) Progress payment No. 03 Payment period ending: 07-20-10 ROYAL ELECTRIC COMPANY 8481 CARBIDE COURT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 674,506.00 189,995.20 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 674,506.00 189,995.20 5. Mobilization 4,500.00 0.00 6. Total Work Completed 679,006.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 679,006.00 189,995.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,995.20