Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-08-22 04-151384 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 53% 04-SCL-680-0.2/0.9 Federal Project: 04-SCL-280-1.5/9.2 ACIM(311) 04-SM-280-21.2/25.9 Progress payment No. 03 Payment period ending: 07-20-10 PACIFIC ELECTRIC CONTRACTING INC 330 PHELAN AVENUE SAN JOSE CA 95112 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 137,448.09 102,786.42 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 137,448.09 102,786.42 5. Mobilization 4,750.00 2,250.00 6. Total Work Completed 142,198.09 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 142,198.09 105,036.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,036.42