Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-16-04 04-151484 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 99% Location: Federal Project: 04-ALA-880 IM 04-ALA-84 NH Progress payment No. 015 Payment period ending: 06-20-20 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,795,984.17 30,100.00 2. a. Extra Work 979,794.34 106,235.29 b. Adustment Comp. 329,341.27 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,105,119.78 136,335.29 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 12,105,119.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,105,119.78 136,335.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,335.29