Dept. of Trans. PROGRESS Serial No. Contract No. 06-167-07-37 04-151914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 39% 04-VAR Federal Project: ACST-000C(285) P-000C(285) Progress payment No. 05 Payment period ending: 06-20-06 PRISM ENGINEERING INC 630 REED STREET SANTA CLARA CA 95050 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 714,449.40 149,682.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 714,449.40 149,682.50 5. Mobilization 175,750.00 0.00 6. Total Work Completed 890,199.40 7. Deductions -11,047.18 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 879,152.22 149,682.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,682.50