Dept. of Trans. PROGRESS Serial No. Contract No. 07-111-08-13 04-152904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 22% 04-SOL-80-5.6/R28.4 Federal Project: 04-NAP-80-6.8/8.0 NONE Progress payment No. 02 Payment period ending: 04-20-07 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 02289 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,641.60 85,837.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 106,641.60 85,837.60 5. Mobilization 23,250.00 23,250.00 6. Total Work Completed 129,891.60 7. Deductions 8. a.Contract Retentions -10,664.16 -8,583.76 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 119,227.44 100,503.84 10. Reduction Amt to Escrow 11. Payment to Escrow 10,660.00 12. Net Pymt. this Estimate 100,503.84