Dept. of Trans. PROGRESS Serial No. Contract No. 10-263-09-30 04-153404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 29% 04-SM-280-R20.3/R27.3 Federal Project: ARRA-280-1(129) L-280-1(129) Progress payment No. 05 Payment period ending: 09-20-10 TOP GRADE CONSTRUCTION INC 50 CONTRACTORS STREET LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 637,510.35 257,559.00 2.a. Extra Work 53,842.07 21,858.46 b. Adjustment Comp. 3. Materials on Hand 43,009.80 43,009.80 4. Earned Subject to Retention 734,362.22 322,427.26 5. Mobilization 194,750.00 41,000.00 6. Total Work Completed 886,102.42 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 929,112.22 363,427.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 363,427.26