Dept. of Trans. PROGRESS Serial No. Contract No. 23-257-21-10 04-160304 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 75% Location: Federal Project: 04-ALA-84-13.0/13.6 ACNH-P084(54) Progress payment No. 031 Payment period ending: 09-20-23 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,145,962.75 166,375.00 2. a. Extra Work 2,011,996.71 600.00 b. Adustment Comp. 10,384.36 0.00 3. Materials on Hand 28,892.94 -32,634.52 4. Earned Subject to Retention 16,197,236.76 134,340.48 5. Mobilization 1,740,000.00 0.00 6. Total Work Completed 17,908,343.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,937,236.76 134,340.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 134,340.48